The tee box renovation project is progressing along better than expected on this second week and we can see the light at the end of the tunnel now, with construction nearing the final few tee box locations. Weather has been fantastic this past week and the crew made huge progress with the dry and cool temperatures. We now have 14 tee boxes completed and seeded with only 7 left to complete. The construction crew is doing a fantastic job on all the many details related to the scope of the project and leaving behind virtually no damage to the course.
#3 Back Tee
#2 Forward Tee
#1 Forward Tee
#10 Forward Tee
#8 Forward Tee
#8 Back Tee
#17 Forward Tee
#18 Back, Middle, Senior (New), Forward
#16 Forward Tee